Winter  2005, Vol. 12 No. 2

Water Main Rehabilitation Projects: Keeping Our System in Top Shape

This past summer, the Authority completed the 2005 Water Main Rehabilitation Project, which was located in Upper Chichester Township, Delaware County. The project focused on three areas: the area of Chichester Avenue between Boothwyn Road and Thornton Road, all of Thornton Road, and Fleming Lane; the area of McCay Avenue and 5th Avenue; and the area of McCay Avenue north on Chichester Avenue to the bridge, Clements Avenue, Randall Avenue, Galbraith Avenue, Sharpless Avenue, Johnson Avenue, Twadell Drive, and Mason Street.

 

Approximately 1,200 feet of 8-inch-diameter and 8,300 feet of 6-inch-diameter water main were rehabilitated in the three areas. An additional 600 feet of 8-inch-diameter and 400 feet of 6-inch-diameter new water main were installed and nearly 40 water services were renewed. Also included in the project areas was the renewal of eight fire hydrants. The total cost of the project was $911,000.

The 2006 Water Main Rehabilitation Project will be performed in the City of Chester on the following streets:

Thurlow Street from 2nd Street to 4th Street

Highland Avenue from 3rd Street to 4th Street, and 6th Street to 15th Street

Hayes Street from 2nd Street to 4th Street

Wilson Street from 2nd Street to 9th Street

 W. 4th Street from Booth Street to Wilson Street

W. 6th Street from Highland Avenue to Ward Street

W. 7th Street from Highland Avenue to Ward Street

Kerlin Street from 2nd Street to 7th Street


 

W. 5th Street from Kerlin Street to Parker Street
 

These projects are part of an ongoing program of refurbishing older water mains in the distribution system. Since the Authority established this water main rehabilitation program in 1974, over 43 miles of water main have been improved, along with the associated valves, service lines, and fire hydrants. The estimated cost of the 2006 project is $1,268,000.

As a result of our rehabilitation projects, residual water pressures and hydrant flows are increased and pipe leakage is decreased.

Route 291 Project Completed: A Cooperative Success Story

In July 2005, the Authority completed replacement of 10,250 feet of 6- and 10-inch-diameter cast-iron water main with 8-inch-diameter water main as part of the Pennsylvania Department of Trans- portation (PennDOT) reconstruction of Route 291 (2nd Street) and side streets in the City of Chester. The project was the single largest water main renewal and relocation project ever undertaken by the Authority with PennDOT. After completing the water main
and service renewals, the Authority continued working with the PennDOT contractor as the concrete for new curbs and sidewalks was poured to ensure proper adjustment of the heights of curbside service boxes and meter boxes.

 

The total estimated cost of the water main renewal and relocation work (including the relocation of a 20-inch- diameter water main, completed earlier) associated with this PennDOT project is $2.8 million. PennDOT has agreed to pay $1.5 million of this cost. The Authority’s Capital Program is funding the remaining $1.3 million. This work was a continuation of PennDOT’s Route 291 reconstruction project, Phase 1 of which was completed in 1999. As a result of this work, Route 291 has been renewed from Eddystone Borough to Trainer Borough. 

This project is an integral part of the economic improvement plan for the City of Chester. The success of this complicated project was due to the close coordination by the Authority, PennDOT, and the PennDOT contractor.


Other articles in this issue:

Page 1

Where Does Your Water Come From?
Getting Educated About H2O! 

 

Page 2

   

Octoraro Treatment Plant Projects:  Clean Drinking Water Today and Tomorrow
East Marlborough System Improvements: Better Services for More Customers

 

Page 4

   

CWA: History on Display!
Preparing Your Water Service for Cold Weather