Winter 2005, Vol. 12 No. 2

Octoraro Treatment Plant Projects:  Clean Drinking Water Today and Tomorrow

Octoraro Treatment Plant Projects to Begin in Spring 2006

Construction is expected to begin in spring 2006 on two projects in CWA’s 10-year capital improvement plan for the Octoraro Treatment Plant and the Susquehanna Pumping Station. Each project has several components. At the Octoraro Treatment Plant, along with other enhancements to the treatment process we will be installing a blend tank that will produce a homogeneous mix of the waters from the Octoraro Reservoir and the Susquehanna River, allowing for more efficient treatment. At the Susquehanna Pumping Station, we are installing a fourth pump and motor with variable flow capability. This will allow us greater flexibility in transferring water to the Octoraro Treatment Plant, reducing pumping costs and improving treatment efficiency. We anticipate that these initial projects will be completed in the early to middle part of 2007, at an estimated total cost of $7.4 million.

These projects are based on a comprehensive review of the Treatment Plant that was completed in 2004. Once these initial projects are completed, the schedule for the other recommendations of the 2004 study will be evaluated and implemented. The projected total cost of the Plant’s capital improvement program is approximately $48 million.

Chlorine Scrubber Project Completed

Construction of a chlorine scrubber system at the Octoraro Treatment Plant was completed in May 2005 as part of the Authority’s existing improvement program for the Treatment Plant. This safety enhancement will contain and neutralize the potentially hazardous condition that could result in the unlikely event that a chlorine cylinder were damaged or malfunctioned. CWA has used chlorination to disinfect finished water at the Octoraro Treatment Plant since 1951. Proper management of this key element in our treatment process is essential to ensure safety. The project cost was $370,000.

Tainter Gate Bulkhead Under Construction

In September 2005, construction began on a floating bulkhead that will enable the Authority to fully inspect, refurbish, and maintain the Tainter gates on the dam at
our Octoraro Reservoir. The contractor is fabricating the bulkhead to the gates’ exact dimensions. Each Tainter

 

the gates’ exact dimensions. Each Tainter gate is 44 feet wide by 30 feet high and is supported by concrete abutment walls and a common concrete center pier. The function of the gates is to contain and control the water flow from the Octoraro Reservoir. The gates are normally in a closed position and are primarily operated during flood events. A propane-fueled engine and auxiliary electric generator are available as standby power sources.  

The Federal Energy Regulatory Commission (FERC) requires all owners of dams with Tainter gates in the United States to assess the gates’ structural soundness and correct any deficiencies.  

An underwater survey of the Tainter gates was completed in October 2005, and the majority of the rehabilitation work will take place in 2006, after the bulkhead is delivered. The bulkhead will be launched onto the reservoir, where it will be sunk upstream of the gates to enable the gates
to be de-watered and work to proceed. Steel plates will be welded on the sides of the Tainter gate beams to satisfy FERC requirements. At the same time, the lifting chains will be replaced and the upstream faces of the gates recoated. We estimate that the project will be completed in
April 2007 at a total cost of $1.5 million. The Authority will also use the bulkhead to test the gates every 5 to 10 years with a full 30-foot opening, as required by FERC.

East Marlborough System Improvements: Better Services for More Customers

In 2005, the Authority continued a multiphase expansion and reinforcement project to tie together two existing distribution systems in East Marlborough Township, Chester County. The project will enhance reliability for our customers in this area. Phases 2 and 3 of this project were completed in 2005, providing service to existing homes. In September 2005, the Distribution Department began Phase 4 of the project, which involves installation of an additional 2,850 feet of 8-inch-diameter water main. Phase 4 will be completed in 2005, at an estimated cost of $142,000. The Authority will add approximately 85 new customers by the completion of Phase 4.

 

Other articles in this issue:

Page 1

Where Does Your Water Come From?
Getting Educated About H2O! 

 

Page 3

   

Water Main Rehabilitation Projects: Keeping Our System in Top Shape

Route 291 Project Completed: A Cooperative Success Story

 

Page 4

   

CWA: History on Display!

Preparing Your Water Service for Cold Weather